Epe Uniper L-Gas gas storage · fill level today: Epe Uniper L-Gas is 82.4% full
One German storage site as reported to GIE AGSI+ for the latest gas day. The forecast and its range are made for Germany as a whole, not per site.
In brief
Epe Uniper L-Gas was 82.4% full on gas day 26 November 2026: 1.3 of 1.6 TWh of working gas. Thirty days earlier it was 83.8% full, and a year earlier, on gas day 26 November 2025, 75.9%. On that day it withdrew 4 GWh net. It holds 0.7% of Germany's working gas volume, the 36th largest of 45 German storage sites (salt cavern storage). Germany as a whole was 53.8% full on the same day.
| Fill level | 82.4% |
|---|---|
| Gas in storage | 1.32 TWh |
| Working gas volume | 1.61 TWh |
| 30 days earlier | 83.8% (27 October 2026) |
| A year earlier | 75.9% (26 November 2025) |
| Injection | 0 GWh/d |
| Withdrawal | 4 GWh/d |
| Share of Germany | 0.7% |
| Location | Epe, North Rhine-Westphalia |
| Type | salt cavern storage |
| Operator | Uniper Energy Storage |
| EIC | 21W000000000065W |
Source: GIE AGSI+, facility-level reporting. Location: LBEG, Untertage-Gasspeicherung in Deutschland (2025).
Reported outages
Planned and unplanned limits on injection or withdrawal that the site's operator reported to GIE AGSI+ under REMIT. The description is the operator's own, usually in English. A report says what may be unavailable, not what happened to the fill.
Running or announced
| When | Kind | Unavailable | Operator's description |
|---|---|---|---|
| 12 October 2026 to probably 18 December 2026 | planned | injection 24.0 GWh/d | Maintenance of compressor. Possible restriction: Reduction of injection rate by up to 50% |
| 11 January 2027 to probably 26 February 2027 | planned | injection 24.0 GWh/d | Maintenance of compressor. Possible restriction: Reduction of injection rate by up to 50% |
| 14 January 2027 | planned | injection 18.0 GWh/d, withdrawal 45.0 GWh/d | Test of safety equipment. Possible restriction: Entire storage facility n/a, but not affecting the delivery of the SCB-Product of THE |
Ended in the last 90 days
| When | Kind | Unavailable | Operator's description |
|---|---|---|---|
| 28 September 2026 to probably 22 October 2026 | planned | withdrawal 36.0 GWh/d | Container inspection FW 22. Possible restrictions: Reduction in withdrawal capacity by up to 30% |
| 2 October 2026 to probably 16 October 2026 | planned | injection 48.0 GWh/d, withdrawal 120.0 GWh/d | Installation of a new control loop. Possible restriction: Entire storage facility n/a |
| 8 October 2026 | planned | injection 18.0 GWh/d, withdrawal 45.0 GWh/d | Test of safety equipment. Possible restriction: Entire storage facility n/a, but not affecting the delivery of the SCB-Product of THE |
| 6 October 2026 to probably 7 October 2026 | planned | injection 46.0 GWh/d, withdrawal 115.0 GWh/d | Maintenance work Power supply. Possible restriction: Entire storage facility n/a |
| 1 September 2026 to probably 25 September 2026 | planned | withdrawal 60.0 GWh/d | Maintenance of preheater. Possible restrictions: Reduction in withdrawal capacity by up to 50% |
Comparable storage sites
German sites of the same type as Epe Uniper L-Gas, with a working gas volume within a factor of two.
| Site | Working gas | Fill | A year earlier |
|---|---|---|---|
| Reckrod · salt cavern storage | 1.61 TWh | 74.2% | 97.1% |
| Lesum · salt cavern storage | 1.69 TWh | 58.4% | 93.5% |
| Epe-NL-RWEGSWEST · salt cavern storage | 1.70 TWh | 86.8% | 82.6% |
| Etzel ESE (MET) · salt cavern storage | 1.51 TWh | 21.5% | 93.8% |
Same location, same operator
What this means for Germany
Questions and answers
- How full is the Epe Uniper L-Gas gas storage?
- Epe Uniper L-Gas was 82.4% full on gas day 26 November 2026: 1.3 of 1.6 TWh of working gas. Thirty days earlier it was 83.8% full, and a year earlier, on gas day 26 November 2025, 75.9%.
- Where is Epe Uniper L-Gas and who operates it?
- Epe Uniper L-Gas lies in North Rhine-Westphalia. It is operated by Uniper Energy Storage, which reports it to GIE AGSI+ under the EIC code 21W000000000065W.
- How large is Epe Uniper L-Gas?
- Its working gas volume, the gas it can store and withdraw, is 1.6 TWh. It holds 0.7% of Germany's working gas volume, the 36th largest of 45 German storage sites (salt cavern storage).
- Why is Epe Uniper L-Gas fuller or emptier than Germany as a whole?
- A single site's fill follows its customers' bookings and says little about supply as a whole. Germany's figure is the sum over all sites, and the 14-day forecast and its range are made for that sum, not per site.
- How often are the figures updated?
- Operators report each gas day (06:00 to 06:00 German time) to GIE AGSI+ the following evening. This page reads AGSI+ twice a day, in the evening and early in the morning.
Storage by location and operator
Locations: Etzel 68% · Epe 76% · Nüttermoor 42% · Jemgum 55%
Operators: Uniper 65% · EWE 46% · SEFE 34% · RWE 86% · Storengy 55% · VNG 58% · MET 45%
Other German storage sites
Rehden 22% · VGS Storage Hub (Bernburg, Bad Lauchstädt, Katharina) 58% · Epe Uniper H-Gas 79% · Breitbrunn 6% · Etzel ESE (Uniper Energy Storage) 65% · Etzel EKB 68% · Etzel Erdgas Lager EGL 95% · Uelsen 47% · Jemgum H (SEFE Storage) 61% · Bierwang 78% · VSP NORD (Rehden, Jemgum) 54% · STASSFURT-RWEGSWEST 81% · INNEXPOOL-RWEGSW 90% · Inzenham-West 4% · Etzel ESE (OMV) 37% · EWE H-Gas Zone 45% · Wolfersberg 1% · Peckensen 84% · Jemgum H (EWE) 41% · Ronnenberg-Empelde 98% · Enschede - Epe (Nuon) 72% · Epe-DE-RWEGSWEST (Epe-L prior to 1 April 2026) 88% · Nüttermoor H-3 85% · Nüttermoor H-2 12% · VGS Zone MND ESG (UGS Stockstadt + UGS Haehnlein) 28% · Kraak 79% · Etzel EGL (Equinor Storage Deutschland) 70% · Epe Trianel 68% · Etzel EnBW (VGS) 73% · Nüttermoor H-5 26% · Epe (MET Epe Speicher) 39% · Etzel EDF (VGS) 54% · Schmidhausen 33% · Epe-NL-RWEGSWEST 87% · Lesum 58% · Reckrod 74% · Etzel ESE (MET) 21% · Enschede - Epe (Eneco) 65% · EWE-Zone L 52% · Harsefeld 61% · Etzel ESE (VGS) 65% · Frankenthal 0% · Rüdersdorf H 88% · TEP Storage Hub (Allmenhausen, Kirchheiligen) 76% · Kiel-Rönne 23%